It is Monday, 6:45 AM. The order count came in 20% over last Monday. The supervisor has 14 people on the schedule and a gut feeling that it is not enough. By 2 PM she is calling the temp agency, and the temps show up at 4.
My position: staffing is arithmetic, not instinct. You already have every number you need. They are just never in one place.
How the math works
- Lines a day = orders x lines per order
- Pick hours = lines / lines picked per hour, x peak factor
- Pack hours = orders / orders packed per hour, x peak factor
- Productive hours per person = shift hours x productive share
- People per shift = hours / shifts / productive hours, rounded up
The productive share covers breaks, the start-up meeting, getting a handheld, and the walk to the first pick. Nobody picks for 8 hours of an 8 hour shift.
The worked example
A floor shipping 2,000 orders a day, 1.5 lines per order, one 8 hour shift. Pickers do 80 lines an hour. Packers do 40 orders an hour. People are productive 80% of the shift. Plan for a day 20% busier than average. Loaded labor cost is $22 an hour.
- Lines: 2,000 x 1.5 = 3,000 a day
- Pick hours: 3,000 / 80 = 37.5, x 1.2 peak = 45 hours
- Pack hours: 2,000 / 40 = 50, x 1.2 peak = 60 hours
- Productive hours per person: 8 x 80% = 6.4
- Pickers: 45 / 6.4 = 7.03, rounded up to 8
- Packers: 60 / 6.4 = 9.4, rounded up to 10
- People on the shift: 18
Paid hours: 18 x 8 = 144. Workload against staffed time: 105 hours of work over 18 x 6.4 = 115.2 productive hours, or 91%.
Labor cost: 144 hours x $22 = $3,168, over the 2,400 orders of a peak day. That is $1.32 per order for pick and pack.
Two things stand out.
Packing is the bigger job here. At 1.5 lines an order, the packer touches every order and the picker touches lines. On a floor like this, cutting pack time does more than speeding up picks.
7.03 pickers costs you 8. That 0.03 is a whole person. Cross-train one packer to pick for an hour and you staff 7 pickers instead of 8.
Common mistakes
Using your best picker's rate. Plan with the median, not the record. A rate over 150 lines an hour is fast for discrete picking. If your plan uses one, check it against what your team actually does.
Planning at 100% productive. 8 paid hours is not 8 picking hours. Breaks alone take a chunk. Time a real shift once.
Staffing to the average day. Average days do not miss carrier cutoffs. Peak days do. Use a peak factor from your own order history, not a guess.
Forgetting the pack line. A staffing plan that starts and ends with pickers backs up at the pack line, and then pickers stand around waiting for totes.
Rounding each role separately and stopping there. Rounding up every role leaves slack. Cross-training is how you spend it.
Tomorrow morning
Pull last week's lines picked and hours worked by person from your system or your timecards. Divide to get lines per hour for each picker. Use the middle number as your rate, not the top one.
Then put your volume and that rate into the free warehouse labor calculator and compare its answer with today's schedule.