One buyer orders a full truckload every quarter because the freight is cheaper. The racks fill, the overflow goes to the dock floor, and the receiving team spends two days putting it away. The next buyer orders every week. Now receiving sees the same supplier 52 times a year.
My position: both buyers are guessing. The order size has a cost on each side, and the economic order quantity is where those two costs meet.
The formula
Three inputs:
- D, annual demand in units
- S, the cost to place and receive one order
- H, the cost to hold one unit for a year (unit cost x holding rate)
EOQ = square root of (2 x D x S / H)
At the EOQ, the yearly cost of placing orders equals the yearly cost of holding stock. Order less and you place too many orders. Order more and cash sits on the shelf.
The worked example
A SKU sells 12,000 units a year. It costs $75 to place and receive one order. The unit cost is $20 and the holding rate is 25% a year.
- H = $20 x 25% = $5.00 per unit per year
- EOQ = square root of (2 x 12,000 x 75 / 5) = square root of 360,000 = 600 units
- Orders a year: 12,000 / 600 = 20, one every 365 / 20 = 18.3 days
- Ordering cost: 20 x $75 = $1,500 a year
- Holding cost: average inventory of 600 / 2 = 300 units x $5 = $1,500 a year
- Total: $3,000 a year
Average inventory is 300 units, or $6,000 at cost.
Now the real world. The supplier ships in cases of 48. 600 / 48 = 12.5 cases, so round up to 13 cases, or 624 units.
- Orders a year: 12,000 / 624 = 19.2, one every 19 days
- Ordering cost: $1,442.31
- Holding cost: 312 x $5 = $1,560.00
- Total: $3,002.31
Rounding to the case pack costs $2.31 a year. That is the useful part of EOQ: the total cost curve is flat near the answer. Order 20% more or 20% less than the EOQ and the yearly cost goes up less than 3%. Round to a case, a layer or a pallet and stop worrying.
Common mistakes
Setting the holding rate too low. Holding cost is not just interest. It is storage space, insurance, shrink, damage and stock that goes obsolete. The 25% here is an editable assumption. Use your own.
Counting only the PO in the order cost. Placing an order costs the buyer's time. Receiving it costs a dock door, a check-in, putaway and the invoice match. Leave those out and EOQ tells you to order too often.
Using EOQ for seasonal items. EOQ assumes steady demand. For a SKU that sells half its year in eight weeks, it is the wrong tool.
Ignoring price breaks. EOQ does not know about the 5% discount at 1,000 units. Run the total cost at the break and compare.
Treating EOQ as the reorder point. EOQ tells you how much. It does not tell you when. Pair it with a reorder point.
Tomorrow morning
Ask your buyer and your receiving lead what one PO really costs, start to finish. Write down the minutes for each step and multiply by loaded wages. That number is your S, and now it is on paper instead of in two people's heads.
Then run your top 10 SKUs through the free EOQ calculator and set the order multiple to the case pack.
OpsBox watches on-hand against your reorder points and receives every PO by scan, so the order you planned is the stock you actually have.